Mulberry Avenue and East 2nd Street Roundabout

PROJECT UPDATE: APRIL 3, 2020

032420 Roundabout 004 (JPG)

Most of the underground work on The Mulberry Avenue-2nd Street Roundabout Project has been completed with the contractor working on grading for the next few weeks before the area is proof rolled and rock added. Pavement restoration is tentatively scheduled to begin in mid-April with the project wrapping up by the end of May, depending on the weather.

Mulberry Avenue is currently closed from the #1 Alley to 3rd Street and 2nd Street is closed from Mulberry Avenue to Orange Street. Eastbound traffic on Mississippi Drive is detoured at Iowa Avenue to 5th Street to Park Avenue. The detour will remain in effect until the project is completed.

CONSTRUCTION DETOUR - Truck traffic heading east on Mississippi Drive will be detoured onto Iowa Avenue, to 5th Street, and down to Oak between returning to 2nd Street. The reverse will be in effect for truck traffic heading west (2nd Street to Oak to 5th Street to Iowa to Mississippi Drive). To ensure the safety of construction workers and the public, drivers are urged to find alternate routes when possible, use caution when traveling in or around the construction area, and pay attention to traffic control signs.

Background

Heuer Construction was awarded the $2.114,738 contract for the Mulberry Avenue and East 2nd Street Roundabout Project by the Muscatine City Council at the April 15, 2019, meeting. The construction primarily consists of pavement removal, excavation, concrete paving, sub-drains, granular sub-base, underground utility improvements, concrete pavers, and streetscape amenities.

Mulberry Roundabout Project Manual Cover Sheet (JPG)
Mulberry Roundabout Overlay (JPG)

MULBERRY & 2ND STREET ROUNDABOUT