Phase 5 West Hill Sewer Separation Project (WHSSP)

Road Closure Diagram August 25, 2022

West Hill Phase 5 Road Closure Diagram 08-25-2022 (JPG)

Detour Map - April 4, 2022

04-04-22 8th_Lucas_Intersection (JPG)

Update: AUGUST 29, 2022

Underground sewer installation as part of the West Hill Sanitary & Storm Sewer Separation Project Phase 5 has moved through the Lucas and Main streets intersection. Hagerty Earthworks, Inc., the prime contractor for Phase 5, has closed the intersection to traffic and established a detour for traffic coming up Main Street using George Street to Green Street and back to Lucas.

Lucas Street remains closed from west of the West 8th Street intersection through the Bush Street intersection. Underground work in that section has been completed and the roadway prepped for paving. The contractor anticipates paving to being on Wednesday depending on the weather. That section of the project could be reopened to traffic the first week of September if the weather cooperates.

Lucas Street also remains closed east of the West 8th Street intersection as underground sewer replacement continues toward Green Street. Limited access is allowed east and south of the Main Street intersection with limited parking.

The 700 block of Climer Street will be closed to all traffic beginning Monday as pavement restoration begins from the alley at 700 Climer to just past the High Street intersection. No parking signs were put out Friday morning ahead of the reconstruction work.

Logan Street is closed from Lucas to the alley in the mid-1100 block with limited access from the alley to Climer Street. Sewer work is proceeding on Logan from Lucas toward Climer. Once completed the block will be prepped for pavement replacement and underground work in the 800 and 900 blocks of Climer will begin.

Pavement replacement is wrapping up in the 700 block of Climer and the High Street intersection. Both will be opened to local traffic only once all driveways and sidewalks are completed.


081222 West Hill Lucas Street prepping street for paving (JPG)



Task
Tentative 
Start Date
Tentative 
End Date
Sewer installation 
Lucas (Busch to Green)
3/21/226/10/22
Sewer Installation
Climer (West 8th to Logan)
3/21/227/08/22
Grading & Paving  Lucas
(Busch to Green)
4/18/227/08/22
Grading & Paving  Climer
(West 8th to Logan)
5/02/228/19/22
Sewer Installation
Climer (Logan to Lucas)
7/11/229/30/22
Waterman installation
Climer (Logan to Lucas)
8/22/229/30/22
Grading & Paving Climer
(Logan to Lucas)
10/03/2211/11/22
Sanitary Sewer Ravine
Hill Street to Logan Street
11/21/222/10/23
Sewer Installation
Logan (Climer to Lucas)
3/20/23
4/28/23
Grading & Paving Logan
(Climer to Lucas)
4/17/235/26/23
Sewer Installation
Lucas (Logan to Fletcher)
5/01/236/09/23
Grading & Paving Lucas
(Logan to Fletcher)
6/05/237/14/23
Sewer Installation
Climer and Lucas area including Knott Avenue
6/12/237/21/23
Grading & Paving
Climer and Lucas area including Knott Avenue
7/17/238/25/23


WHSSSP Phase 5 Project Area

Overall Phase 5 Map (JPG)

Contact Information:

City Engineer:  Pat Lynch  (563) 263-8933

City Project Manager:  Steve Dalby  (563) 299-2888

Contractor:  John Hagerty  (563) 260-3877


Background:


Hagerty Earthworks, Inc., was awarded the $6.03 million contract for Phase V of the WHSSP during the April 1 City Council meeting. This phase includes replacing sewers on West 8th Street from Broadway to Lucas, on Climer Street from West 8th Street to Lucas, Logan Street from Lucas to Climer, Lucas Street from 912 Lucas to Fletcher Avenue, and through the ravine between Climer and Lucas.

Street intersection geometry changes planned

Phase 5 of the West Hill Sanitary and Storm Sewer Separation Project will be replacing the remainder of 8th Street along with a portion of Lucas Street during the 2021-2023 construction seasons. During this time, the City of Muscatine plans to correct some street intersection geometry. Below are renderings of some of the proposed changes that will occur during Phase 5.

WHSSP Phase 5 West 8th Street - Broadway to Locust (JPG)
WHSSP Phase 5 West 8th Street and Climer intersection (JPG)
WHSSP Phase 5 West 8th Street and Locust intersection (JPG)
WHSSP Phase 5 Lucas and Climer intersection (JPG)