Phase 5 West Hill Sewer Separation Project (WHSSP)

Road Closure Diagram April 11, 2022

Road Closure Diagram 4-11-2022 (JPG)

Detour Map - April 4, 2022

04-04-22 8th_Lucas_Intersection (JPG)

Update: MAY 16, 2022

Underground work for sanitary and storm sewer construction along with water main work are currently underway in two locations as part of  Phase 5 of the West Hill Sanitary & Storm Sewer Separation project.

The West 8th and Lucas intersection is currently closed to all traffic with Climer Street reduced to local traffic only from West 8th to High Street. The West 8th/Lucas intersection will be closed for approximately 4-6 more weeks as underground work and pavement restoration is completed. Work is also underway to complete the section of West 8th from Broadway to Lucas. Once all West 8th work is completed, traffic will be able to use West 8th. 

Lucas will remain closed between West 8th and Busch as sewer separation and pavement restoration work begins. 

Portions of Climer will be closed throughout the summer and fall. Climer Street residents will be updated regarding street closures in their immediate area as the construction moves toward Logan, and then between Logan and Lucas. Updates to the Road Closure Diagram and Detour map will be provided as the status of the closures changes. Everything is subject to change and dependent on weather conditions.

The Contractor will work to keep all driveways accessible for residents from Busch Street to Main Street as much as practical but periodic closures are possible during what is anticipated to be a 4-to-6-week construction period. The goal of the Contractor is to have the sewer work done and the intersection repaved and open within that time frame. Take note that the sewer project construction on Lucas Street during 2022 will ultimately encompass the area from Busch Street to the curve in Lucas Street just past Green Street. That will include the 900, 1300, 1400, and 1500 blocks of Lucas Street this spring and summer. Advance notice will be given before those areas are closed for construction.

051722 West Hill - Lucas and 8th work 01 (JPG)

 



051722 West Hill - Climer. work 02 (JPG)



Task
Tentative 
Start Date
Tentative 
End Date
Sewer installation 
Lucas (Busch to Green)
3/21/226/10/22
Sewer Installation
Climer (West 8th to Logan)
3/21/227/08/22
Grading & Paving  Lucas
(Busch to Green)
4/18/227/08/22
Grading & Paving  Climer
(West 8th to Logan)
5/02/228/19/22
Sewer Installation
Climer (Logan to Lucas)
7/11/229/30/22
Waterman installation
Climer (Logan to Lucas)
8/22/229/30/22
Grading & Paving Climer
(Logan to Lucas)
10/03/2211/11/22
Sanitary Sewer Ravine
Hill Street to Logan Street
11/21/222/10/23
Sewer Installation
Logan (Climer to Lucas)
3/20/23
4/28/23
Grading & Paving Logan
(Climer to Lucas)
4/17/235/26/23
Sewer Installation
Lucas (Logan to Fletcher)
5/01/236/09/23
Grading & Paving Lucas
(Logan to Fletcher)
6/05/237/14/23
Sewer Installation
Climer and Lucas area including Knott Avenue
6/12/237/21/23
Grading & Paving
Climer and Lucas area including Knott Avenue
7/17/238/25/23


WHSSSP Phase 5 Project Area

Overall Phase 5 Map (JPG)

Contact Information:

City Engineer:  Pat Lynch  (563) 263-8933

City Project Manager:  Steve Dalby  (563) 299-2888

Contractor:  John Hagerty  (563) 260-3877


Background:


Hagerty Earthworks, Inc., was awarded the $6.03 million contract for Phase V of the WHSSP during the April 1 City Council meeting. This phase includes replacing sewers on West 8th Street from Broadway to Lucas, on Climer Street from West 8th Street to Lucas, Logan Street from Lucas to Climer, Lucas Street from 912 Lucas to Fletcher Avenue, and through the ravine between Climer and Lucas.

Street intersection geometry changes planned

Phase 5 of the West Hill Sanitary and Storm Sewer Separation Project will be replacing the remainder of 8th Street along with a portion of Lucas Street during the 2021-2023 construction seasons. During this time, the City of Muscatine plans to correct some street intersection geometry. Below are renderings of some of the proposed changes that will occur during Phase 5.

WHSSP Phase 5 West 8th Street - Broadway to Locust (JPG)
WHSSP Phase 5 West 8th Street and Climer intersection (JPG)
WHSSP Phase 5 West 8th Street and Locust intersection (JPG)
WHSSP Phase 5 Lucas and Climer intersection (JPG)