2nd Street Streetscape Project


PROJECT UPDATE: SEPTEMBER 3, 2021

Work in the 100 block of West 2nd Street has been completed with work in the 2nd Street Streetscape Project now concentrating on rebuilding the Chest Street intersection.


The Chestnut Street intersection was closed Monday, August 30, for removal and replacement. The intersection was poured back on Sept. 2 with work on the intersection sidewalks set to begin on Sept. 7.


The intersection was added to the project due to the deteriorated condition of the pavement. Work is expected to be completed by September 20, weather permitting.


The project wraps up with sidewalk replacement and some full depth patching in the 200 block of West 2nd Street. That work is tentatively planned to start on Sept. 20.


All dates are tentative and dependent on weather conditions or other unforeseen circumstances.

 

Access to all businesses in the construction area is being maintained with signage available to direct customers to the businesses.

 

MuscaBus announced a detour for the Blue Route due to construction on East 2nd Street.

 

KE Flatwork, Inc., and staff from the City of Muscatine meets with businesses owners and residents that are affected by the current construction area at 9 a.m. every Thursday. These meetings will be held weekly throughout the construction phase and will move to each affected area as work progresses.

 

Drivers are reminded to slow down and use caution when travelling through the construction zone, obey traffic control devices, and be aware of workers. Use an alternate route if possible.

 

The entire project is expected to be completed by Fall 2021, weather permitting.

Residents or business owners who have questions about the project, the schedule of work, or would just like more information about the project can call the Department of Public Works or send a comment or concern, by email to feedback@muscatineiowa.gov or pwrequest@muscatineiowa.gov

090221 2nd Street Chestnut Intersection pour (1) (JPG)

2021 Tentative Project Schedule

*Schedule is subject to change and will be updated weekly during onsite public meetings. 

*Public meetings will be held onsite with exact place TBD on Thursdays at 9 a.m.

*Sidewalks will always be open on one side of the road.

 

 

2nd Street and Chestnut Intersection 

August 30 to September 20 

Complete reconstruction of intersection

 

2nd Street - Chestnut to Pine 

September 20 to October ?

Sidewalk replacement 

Some full depth patching of driving lanes

One lane will always be open

 

2nd Street - Finish up Project 

September 27 to October ?

One lane will always be open

 

2nd Street and Iowa Intersection 

June 14 to July 26

Opened July 9

 

2nd Street - Sycamore to Iowa 

May 17 to July 9

Opened July 9

 

2nd Street and Sycamore intersection

March 15 to May 17

Opened May 17

 

2nd Street - Mulberry Ave to Walnut

March 29 to April 30

Opened April 30

 

2nd Street - Iowa to Chestnut Street 

July 26 to August 30

Opened August 30 


Background

The 2nd Street Project is comprised of sidewalk, roadway, utility, and streetscape construction on 2nd Street from Mulberry Avenue to Pine Street. Construction primarily includes pavement removal, excavation, concrete sidewalks, concrete roadway paving, underground utility improvements, concrete pavers, and streetscape amenities.

The Muscatine City Council awarded the $2.9 million contract for the 2nd Street Streetscape Project to KE Flatwork, Inc., of Elbridge, Iowa, at the February 6, 2020, City Council meeting. KE Flatwork, Inc., was the lowest of four bidders for the two-year project.

2019.11.14 - 200 block West 2nd Street (JPG)
2019.11.14 - Iowa Ave intersection (JPG)
2019.11.14 - Sycamore to Cedar (JPG)
2019.11.14 - Cedar to Walnut (JPG)

Scope of the Project

The 2nd Street Streetscape Project comprises sidewalks, roadway, utilities, and streetscape construction located on 2nd Street from Mulberry Avenue to Pine Street. Construction primarily includes pavement removal, excavation, concrete sidewalks, concrete roadway paving, underground utility improvements, concrete pavers, and streetscape amenities.

Work will be completed over a two-year period. Bids were opened on January 16, 2020, with the contract to be awarded by the Muscatine City Council at its February 6, 2020, regular meeting.

2nd Street Reconstruction Project Plans (PDF)

2nd Street Reconstruction Project Bid Set - Specs (PDF)

2nd Street Reconstruction Project Bid Set -  Plans (PDF)


Economic Programs

Several programs are being offered by the Department of Community Development for property improvements that may be used by building owners and/or business owners in conjunction with or in addition to the Streetscape Project. 

The programs include: 

2nd Street Presentation to Council 04-09-2020

04-08-20 Map showing Stage 5 of Street-Scape Project (JPG)