West Hill Sewer Separation Project Phase 4

4B Road Closure Diagram 3-21-19 (JPG)

UPDATE MAY 16, 2019

Sanitary, storm, and water main work has been completed in the 700 block of Sycamore and the 200 block of East 8th Street by KMA Excavating with KE Flatworks expected to begin prepping those two blocks for pavement on Monday, May 20. KMA Excavating will continue sanitary and storm work up to Iowa in the100 block of East 8th Street. Water main work has already been completed up to Iowa. Work will move into the Iowa intersection early in June. An exact date to close the intersection has not been set as yet but the intersection work will be completed by July 3 according to the contractor's schedule.

THE PROJECT

The West Hill Area Sanitary and Storm Sewer Project Phase 4B began on March 21, 2019, in the 100 and 200 blocks of East 8th Street and the 700 block of Sycamore Street. Phase 4B includes replacement of water main along with storm and sewer mains. The red area (map above) is where Phase 4B will be through July 3, 2019. The pink areas are the rest of the areas where work will be done during 2019. Advance notice will be given before those streets are closed to traffic. 

A detour route has been established this week on 7th Street from Cedar to Broadway to provide the best path for traffic flow and return to West 8th Street at a traffic signal-controlled intersection. Heavy truck traffic is re-routed away from the residential area. In order to provide a detour route through this neighborhood that is safer for traffic and parked vehicles, parking is limited to one side only on 7th Street. No Parking signs were placed on the river side (even number side) to prohibit parking beginning Wednesday, March 20.

The project will be completed in two parts to ease the disruption of traffic on one of Muscatine’s busiest streets. Sewer replacement and replacement of the pavement will be completed from Cedar to Iowa during the first part that is expected to be completed by July 3. The second part from Iowa to Lynn is tentatively scheduled to begin on July 7 and anticipated to be completed by September 23. The entire project has an end date of October 4, 2019, weather permitting.

Phase IV Area MapContractor

The contract for Phase 4 of the West Hill Sewer Separation Project was awarded to KE Flatwork, Inc., Eldridge, Iowa, on April 5, 2018, in the amount of $6,109,522.45.

Background Information:

In 2004 Stanley Consultants Inc. signed a contract with the city to proceed with a study and projects for the West Hill area. On September 5, 2007, the city received a stamped Consent Order from the U.S. Environmental Protection Agency requiring that by December 31, 2010, the city would "submit to EPA and IDNR a report describing the projects needed to complete the separation of the remaining combined portions of the sewer system including the West Hill area". The report "shall include a schedule and estimated cost for completing each project identified therein, and an update on the city's plans for financing the projects". Further, "By DECEMBER 31, 2028, completed all projects described . . . above". Four projects have been identified, each estimated at $15 million to be implemented over the next 14 years to comply with the December 31, 2024 Consent Order date.

West Hill Separation Area