Posted on: May 11, 2022

[ARCHIVED] Traffic Alert: East 5th Street closure begins Thursday (May 12)

Asphalt Overlay project repairs to Robin Road repairs (JPG)

MUSCATINE, Iowa – Crews from the Department of Public Works (DPW) have been hard at work this week repairing soft spots on Robin Road, and that work will shift to East 5th Street on Thursday.

 

The 2021-2022 Hot Mix Asphalt Overlay Project is set to resume the week of May 16 with two street sections receiving attention this week from the DPW Street Maintenance Division ahead of receiving new asphalt.

 

Brandt Construction Company will resume milling and putting down an asphalt overlay four street segments and four alley segments as part of the 2021-22 project that is to be completed this spring.

 

The Street Maintenance Division has been repairing soft spots on Robin Road since Monday and will switch to East 5th Street Thursday. Lane restrictions on Robin Road are in place where work is being undertaken. 

 

Meanwhile East 5th Street will be closed to all traffic starting Thursday (May 12) from Mulberry to Orange where most of the soft spots are located. Additional soft spots from Orange to Cypress Streets will also be repaired by DPW crews. Some additional closures and lane restrictions will be implemented over the next three weeks as repairs, milling, and asphalt overlay work on East 5th Street is completed. Work is tentatively scheduled to be completed by June 3, weather permitting.

 

Detour Map for East 5th closure from Mulberry to Orange (JPG)A detour map is posted on the City of Muscatine website or available by clicking 5th Street Detour.

 

Muscatine Power & Water (MPW) has completed the replacement of a water main on Fair Acres Drive from Bidwell Road to Crestline Drive, with that section scheduled to be the first street segment to receive an asphalt overlay by Brandt Construction. The schedule for the other street segments will depend on the repairs to the soft spots on Robin Road (Bidwell Road to Sunrise Circle) and East 5th Street (Mulberry to Cypress). The other street segment that is part of the current contract is Bartlett Street (Mulberry to Cedar).

 

Four alley segments will also be completed in the next two months including the alley between Lincoln Boulevard and Grand Avenue (from Clay to Jackson), the alley between Lake Park Boulevard and McArthur Street (from 2nd Avenue to Lake Park Boulevard), the alley between Taylor and Clinton streets (from New Hampshire to Hershey), and the alley between Mary Place and Orchard Avenue (Orchard Avenue to the Dead End).

 

Lane restrictions will be in place while Brandt Construction mills the streets and alleys, and during the asphalt overlay process. Drivers are urged to use caution when in construction areas and obey traffic control devices and flaggers.

 

 

Drivers are reminded to slow down and use caution when travelling through construction zones, obey traffic control devices, and be aware of construction workers. Use an alternate route if possible.

 

Click on CONSTRUCTION to visit the Department of Public Works Construction Projects page where more information can be found on City of Muscatine construction projects. 

An interactive map is available showing current street closures and street work.

 

If you have a comment or concern, please email feedback@muscatineiowa.gov or pwrequest@muscatineiowa.gov. A staff member will respond within 24 hours.

 