Projects Currently Underway

Cleveland Street Reconstruction Project


This project was awarded to All American Concrete of West Liberty, Iowa, on July 20, 2017, in the amount of $403,889.10.  The project will begin as early as Monday, July 31, 2017, and consists of removing and replacing existing concrete on Cleveland Street from Park Avenue to 2nd Avenue. There will be access provided to businesses at all times. However, there may be some delays. Please be patient. Contract completion date is September 30, 2017. Contact City of Muscatine Public Works at 263-8933 if you have any questions. Pictured below is a guide to the four phases of the project. However, the schedule is not cast in concrete and is contingent upon the requirements of the contractor. The phases may change as needed.

Phases Of Construction


West Hill Sewer Separation Project - Phase 3


Phase 3 project was awarded on April 16, 2015 to Hagerty Earthworks, LLC of Muscatine, Iowa in the amount of $4,988,688.00.  

Update as of July 26, 2017:  

The sanitary and storm sewer work in the 4th Street Park area continues with portions of Broadway and West 4th around the park being closed to traffic.  Notifications of closures will be provided ahead of time as much as is possible. Access on West 4th Street between Locust and Cherry Street is limited, but is still open to some local traffic. The driving surface is less-than-ideal so caution must be taken.  Avoid the area if possible. 

For more information or updated information, call Steve Dalbey at 563-299-2888. 

Background Information:
In 2004 Stanley Consultants Inc. signed a contract with the city to proceed with a study and projects for the West Hill area. On September 5, 2007 the city received a stamped Consent Order from the U.S. Environmental Protection Agency requiring that by December 31, 2010 the city would “submit to EPA and IDNR a report describing the projects needed to complete the separation of the remaining combined portions of the sewer system including the West Hill area”. The report “shall include a schedule and estimated cost for completing each project identified therein, and an update on the city’s plans for financing the projects”. Further, “By DECEMBER 31, 2024, completed all projects described . . . above”. Four projects have been identified, each estimated at $15 million to be implemented over the next 14 years to comply with the December 31, 2024 Consent Order date.


Asphalt Overlay Program 2017


Bids were accepted and a contract was awarded to Illowa Investments, Inc. of Blue Grass, IA on July 20, 2017 in the amount of $519,250.10.    

The list of proposed streets for 2017 follows:
Elfers Street from Grandview Avenue to Dead End
Washington Street from Diagonal Street to River Road
McArthur Street from Lincoln Boulevard to Summit Avenue
Jefferson Street from Lincoln Boulevard to Fillmore Street
Isett Avenue from East 11th Street to Woodlawn Avenue
Cypress Street from East 11th Street to #9 Alley
Howard Street from Clay Street to Jackson Street
Eisenhower Street from Devitt Avenue to Dead End
5th Avenue from Webster Street to Blaine Street
Lincoln Boulevard from Clay Street to Lake Park Boulevard
57th Street from 67th Avenue to rail road tracks 
 

Sidewalk Program 2017

The 2017 Sidewalk program has not been awarded as yet.